Galleria Overbuild


Authority Approvals Tracker – Building Permit Amendment

Building Permit (MePS): #


Municipality and service provider approval for occupancy

EAD NOC

• Environmental approvals

• Environmental impact assessment

Inception


• Confirm affection plans

• Land use approval

• Phasing

• Plot ownership

Registration


• DCR

• Affection plan

• Consultant appointment form

Site clearance


System request to confirm whether there are any major conflicts which must be resolved before project submissions can occur.

Site clearance achieved?
ITC


Approval of the development’s impact to local traffic and road network

• Inception meeting with ITC

• TIS (level 1 / 2 / 3) (for >100 trips/peak)

• Circulation plan

• GIS update

ADCD


Development Civil Defence (emergency services) approval

• Initial engagement

• ADCD drawing set submission (DWF) by FLS

• House of Expertise

• Cover letter for submission (project briefing)

Geotechnical approval


Commissioning of geotechnical investigation and approval of findings by municipality

• Site access request

• Plot demarcation may be required

• Geotechnical BH + MASW/geophysical survey

• Soil interpretive report (approved in MePS)

ADDC LDN


Power supply connection application for ADDC

• Initial engagement

• ADDC single line diagram and General Arrangement (control routes) submission

Estidama PBRS


Sustainability requirements for building development, only applicable for buildings with GFA >2,000 m2. Minimum requirement 1 pearl, government projects must achieve min. 2 pearls

• Scorecard submission to demonstrate required number of “pearls” submitted by PQP.

ADM - Architecture


Municipality architectural approval

• DCR

• Architectural planning drawing set (plans, sections elevations), including code analysis

• Stamped owner design approval form

• Stamped PDF of drawing set (client)

• Unstamped DWF of drawing set (for ADM to stamp/comment)

Contractor assignment


Final submissions required to complete registration of the development contractor

• Plot demarcation (if not completed previously)

• Contractor registration signed and stamped by consultant, contractor and client

ADM - Structures


Municipality structural design submission

• Structure model files

• Structures calculation report

• Populated structures “Smart” spreadsheet

• Structure drawing set

• Structure drawing set stamped by accredited third party reviewer

Work commencement


At this stage the contractor is able to make generate the building permit and make all remaining construction submissions, including fence permits, site clearance permits and construction phase NOCs.

Site utility/environment clearance: #


No objections’ required for impacted site assets. This system is only triggered in some instances where site clearance is not achieved.

ENOC


Objections related to placement of assets on site & connecting services/facilities

• UAE armed forces

• ADAC

• ADDC

• ADNOC

• ADSSC

• DCT

• Al Dhafra Municipality/DRM

• Al Dhafra Municipality / DRM Roads

• Etisalat + Du

• EAD

• UAE Armed Forces – GHQ Military Telecom

• ITC

• MCC

• Tadweer (waste)

• Transco

• Default NOCs (special cases)

Affection plan utilities condition removal


This submission can be made by the consultant or the client. The ‘utilities condition’ will be a bullet pointed item on the affection plan, generally written in arabic with text to the effect of “works may only proceed subject to approval from utility owners”

• ENOC with all objections removed

• Affection plan currently showing utilities condition to remove.

Other authority approvals not linked to building permit


These items can be submitted during construction, some engagement is permitted by authorities during design stage

Telecommunications submission

• Estidama/Du proposal of connection box within building. This must be fully approved before ground floor of building is completed.

• Drawings demonstrating proposed connection location.

ADMCC


Approval of CCTV to be connected to ADMCC network

• Initial engagement

• Printed CCTV coverage drawings stamped by ADMCC

Other project approvals


These items are not UAE authority approvals, but external accreditations the project is targeting.

GBCI LEED

• LEED registration and review submission

• Project registration

• Scorecard submission including evidence (in GBCI portal)

flow