Project Planning and Staffing
Purchase Requisition
Purchase Order
Goods Receipt
Invoice Receipt
Finance Postings
Transfer Actual Cost to Portfolio item (Background)
Finance Settlement
Project Planning and Staffing
Creation of project structure based upon template
Distribute the budget in lower level WBS
Release the WBS
AUC gets created to WBS element
Create Requisition
Commitment PO Cost on WBS
Create Purchase Order
Commitment PO Cost on WBS
Create Goods Receipt
Actual cost on WBS
Create Invoice Receipt
Actual cost on WBS
Vendor Invoice Posting (FB60)
Actual cost on WBS
Other Project Expenses (FB50)
Actual cost on WBS
Roll up cost to item level
Roll up cost to bucket level
Settlement to Cost Center in case of OPEX WBS
Close the Project