Livoa
Discord
Pricing
English
Sign In
2025
2026
Aug Sep Okt Nov Dez Jan Feb Mär Apr Mai Jun Jul Aug Sep Okt Nov Dez
Project Initiation
01.09.2025 - 31.12.2025
Assign project team
Define objectives
Identify key stakeholder
Develop project plan and budget estimate
Requirements Analysis
01.10.2025 - 31.10.2025
Stakeholder workshops
Current As-is processes
Define key requirements
Vendor Evaluation
03.11.2025 - 16.12.2025
Identify shortlist
Cost-benefit analysis
Risk analysis
System Design & Configuration
22.12.2025 - 02.02.2026
Design workshop with vendor
Define user roles
Develop customizations
Configure ERP modules
Implementation & Migration
01.01.2026 - 15.04.2026
Develop migration plan
Cleanse and validate legacy data
Setup new ERP
Finalize migration
User Training & Testing
02.02.2026 - 15.05.2026
Develop user training
UAT testing
Go-Live & Support
01.05.2026 - 30.09.2026
Execute final data migration
System Go-Live
Monitor system performance
Provide hypercare user support
ES
by Tobias
Use this design
0
0 uses